JK0-017 · Question #425
A project manager is using a vendor with a fixed bid contract. The vendor would like to help out with other parts of the project. Which of the following should the project manager do NEXT?
The correct answer is A. Review the vendors SOW and determine if the additional work items can be included. See the full explanation below for the reasoning.
Question
A project manager is using a vendor with a fixed bid contract. The vendor would like to help out with other parts of the project. Which of the following should the project manager do NEXT?
Options
- AReview the vendors SOW and determine if the additional work items can be included.
- BAllow the vendor to accept the additional work on a time and material (T&M) basis.
- CAllow the vendor to accept the additional work, but honor the fixed bid price.
- DExplain to the vendor that the work is already assigned to the vendor with the lowest cost.
How the community answered
(27 responses)- A81% (22)
- B4% (1)
- C4% (1)
- D11% (3)