CompTIA
JK0-017 · Question #420
A project manager notices that status meetings are poorly attended and that one or two team members try to dominate the meetings. Which of the following should the project manager do to make the…
The correct answer is A. Include agenda items in the meeting invitation. B. Ensure that the meetings start and end on time. See the full explanation below for the reasoning.
Question
A project manager notices that status meetings are poorly attended and that one or two team members try to dominate the meetings. Which of the following should the project manager do to make the project status meetings more productive? (Select Two).
Options
- AInclude agenda items in the meeting invitation.
- BEnsure that the meetings start and end on time.
- CProvide criticism to poor team performers.
- DAllow the team members to set the tone of the meeting.
- EDiscuss issues during the meeting until they are resolved.
How the community answered
(51 responses)- A76% (39)
- C14% (7)
- D4% (2)
- E6% (3)
Community Discussion
No community discussion yet for this question.