JK0-017 · Question #418

Who has the MOST control over project scope changes?

The correct answer is D. Change control board. See the full explanation below for the reasoning.

Question

Who has the MOST control over project scope changes?

Options

  • AKey stakeholders
  • BProject sponsor
  • CProject manager
  • DChange control board

How the community answered

(32 responses)
  • A
    13% (4)
  • B
    3% (1)
  • C
    6% (2)
  • D
    78% (25)