JK0-017 · Question #411
The change control board has requested that a project manager evaluate the impact of a major change request that will affect the timetable of several work-packages. Which of the following actions…
The correct answer is A. Create a modified version of the project schedule applying the critical path method. See the full explanation below for the reasoning.
Question
The change control board has requested that a project manager evaluate the impact of a major change request that will affect the timetable of several work-packages. Which of the following actions should the project manager undertake FIRST?
Options
- ACreate a modified version of the project schedule applying the critical path method.
- BCall a project team meeting to use combined expert judgment to accept or reject the change
- CCreate a Pareto chart for the outputs from the specific work-packages identified by the
- DCrash the schedule to meet the original deadlines.
How the community answered
(34 responses)- A79% (27)
- B6% (2)
- C3% (1)
- D12% (4)
Community Discussion
No community discussion yet for this question.