JK0-017 · Question #411

The change control board has requested that a project manager evaluate the impact of a major change request that will affect the timetable of several work-packages. Which of the following actions…

The correct answer is A. Create a modified version of the project schedule applying the critical path method. See the full explanation below for the reasoning.

Question

The change control board has requested that a project manager evaluate the impact of a major change request that will affect the timetable of several work-packages. Which of the following actions should the project manager undertake FIRST?

Options

  • ACreate a modified version of the project schedule applying the critical path method.
  • BCall a project team meeting to use combined expert judgment to accept or reject the change
  • CCreate a Pareto chart for the outputs from the specific work-packages identified by the
  • DCrash the schedule to meet the original deadlines.

How the community answered

(34 responses)
  • A
    79% (27)
  • B
    6% (2)
  • C
    3% (1)
  • D
    12% (4)