The schedule estimates for a particular work package that is underway were not properly considered and the timescales are too tight. Which of the following methods should the project manager select…
The correct answer is B. SPI and SV. See the full explanation below for the reasoning.
Question
The schedule estimates for a particular work package that is underway were not properly considered and the timescales are too tight. Which of the following methods should the project manager select to investigate?
Options
- APDM
- BSPI and SV
- CCPM
- DIssues log
How the community answered
(33 responses)- A6% (2)
- B82% (27)
- C9% (3)
- D3% (1)