JK0-017 · Question #395

Which of the following elements would be needed to prepare an effective project scope document?

The correct answer is C. An approved project charter. See the full explanation below for the reasoning.

Question

Which of the following elements would be needed to prepare an effective project scope document?

Options

  • AAn approved project milestone schedule
  • BAn approved risk assessment document
  • CAn approved project charter
  • DA responsibility assignment matrix

How the community answered

(55 responses)
  • A
    13% (7)
  • B
    4% (2)
  • C
    78% (43)
  • D
    5% (3)