JK0-017 · Question #391

Which of the following occurs during a project kick-off meeting? (Select Two).

The correct answer is D. Project goals are communicated. E. Roles and responsibilities of the project team are identified. See the full explanation below for the reasoning.

Question

Which of the following occurs during a project kick-off meeting? (Select Two).

Options

  • AWork performance information is established.
  • BRisk analysis is performed.
  • CQuality metrics are defined.
  • DProject goals are communicated.
  • ERoles and responsibilities of the project team are identified.

How the community answered

(51 responses)
  • A
    8% (4)
  • B
    18% (9)
  • C
    4% (2)
  • D
    71% (36)

Community Discussion

No community discussion yet for this question.