Which of the following actions would require a formal project closure? (Select Two).

The correct answer is C. The project work is completed. D. The project has run out of money. See the full explanation below for the reasoning.

Question

Which of the following actions would require a formal project closure? (Select Two).

Options

  • AThe project is delayed indefinitely because a required vendor part cannot be delivered.
  • BThe project is producing a product that is no longer compliant with new Federal regulations.
  • CThe project work is completed.
  • DThe project has run out of money.
  • EThe project sponsor has become disinterested in the project.

How the community answered

(33 responses)
  • A
    3% (1)
  • B
    9% (3)
  • C
    76% (25)
  • E
    12% (4)

Community Discussion

No community discussion yet for this question.