A project's Critical Path is:

The correct answer is B. Asequence of activities that takes the longest time to complete. See the full explanation below for the reasoning.

Question

A project's Critical Path is:

Options

  • AAsequence of activities that takes the shortest time to complete.
  • BAsequence of activities that takes the longest time to complete.
  • CAsequence of the activities that can be delayed without impacting the project's end date.
  • DAsequence of the project's activities required to meet the defined milestones.

How the community answered

(45 responses)
  • A
    2% (1)
  • B
    80% (36)
  • C
    13% (6)
  • D
    4% (2)