A project's Critical Path is:
The correct answer is B. Asequence of activities that takes the longest time to complete. See the full explanation below for the reasoning.
Question
A project's Critical Path is:
Options
- AAsequence of activities that takes the shortest time to complete.
- BAsequence of activities that takes the longest time to complete.
- CAsequence of the activities that can be delayed without impacting the project's end date.
- DAsequence of the project's activities required to meet the defined milestones.
How the community answered
(45 responses)- A2% (1)
- B80% (36)
- C13% (6)
- D4% (2)
Community Discussion