Question

A project's Critical Path is:

Options

  • AAsequence of activities that takes the shortest time to complete.
  • BAsequence of activities that takes the longest time to complete.
  • CAsequence of the activities that can be delayed without impacting the project's end date.
  • DAsequence of the project's activities required to meet the defined milestones.