As a result of changes in the economy, it has been communicated that the current costs for needed components have doubled from what was originally budgeted. If the procurement occurs, this would…
The correct answer is A. Evaluate alternatives that could be used that would result in the same scope to be produced. See the full explanation below for the reasoning.
Question
As a result of changes in the economy, it has been communicated that the current costs for needed components have doubled from what was originally budgeted. If the procurement occurs, this would result in exceeding the cost baseline for the project. Which of the following actions should the project manager take?
Options
- AEvaluate alternatives that could be used that would result in the same scope to be produced
- BUse contingency funds to cover the procurement of the components
- CCreate a change request to see if the baselines can be revised to incorporate the appropriate
- DContact the customer to let them know that the costs will be higher, and await approval from the
How the community answered
(30 responses)- A77% (23)
- B3% (1)
- C13% (4)
- D7% (2)