A project team member, Joe, has completed his project work. Although the project is not completed yet, Joe has been assigned by the PMO director to a new project. Which of the following describes…
The correct answer is C. Project based. See the full explanation below for the reasoning.
Question
A project team member, Joe, has completed his project work. Although the project is not completed yet, Joe has been assigned by the PMO director to a new project. Which of the following describes the organization structure Joe works in?
Options
- AFunctional
- BMatrix
- CProject based
- DStrong Matrix
How the community answered
(34 responses)- A3% (1)
- B9% (3)
- C85% (29)
- D3% (1)