A project manager is completing a project schedule network diagram using boxes to represent the project activities that are connected by lines to show their dependencies. Which of the following…

The correct answer is D. PDM. See the full explanation below for the reasoning.

Question

A project manager is completing a project schedule network diagram using boxes to represent the project activities that are connected by lines to show their dependencies. Which of the following tools is the project manager using?

Options

  • AAOA
  • BWBS
  • CADM
  • DPDM

How the community answered

(29 responses)
  • A
    3% (1)
  • B
    10% (3)
  • C
    7% (2)
  • D
    79% (23)