Before a change request is presented to the change control board, which of the following should the project manager do?

The correct answer is B. Evaluate the affect on all other parts of the project. See the full explanation below for the reasoning.

Question

Before a change request is presented to the change control board, which of the following should the project manager do?

Options

  • ASuggest the board study the cost of the change.
  • BEvaluate the affect on all other parts of the project.
  • CReview the change request with the project sponsor.
  • DRequest team member input on the value of the change.

How the community answered

(48 responses)
  • A
    4% (2)
  • B
    75% (36)
  • C
    15% (7)
  • D
    6% (3)