During project execution, the cost management plan would be used to:
The correct answer is D. Determine if variances exceed a defined threshold. See the full explanation below for the reasoning.
Question
During project execution, the cost management plan would be used to:
Options
- AEnsure that resources are compensated fairly.
- BSchedule resources for each phase of the project.
- CIdentify costs that were not previously identified.
- DDetermine if variances exceed a defined threshold.
How the community answered
(26 responses)- A4% (1)
- B8% (2)
- C12% (3)
- D77% (20)