nerdexam
CompTIA

JK0-017 · Question #286

During project execution, the cost management plan would be used to:

The correct answer is D. Determine if variances exceed a defined threshold. See the full explanation below for the reasoning.

Question

During project execution, the cost management plan would be used to:

Options

  • AEnsure that resources are compensated fairly.
  • BSchedule resources for each phase of the project.
  • CIdentify costs that were not previously identified.
  • DDetermine if variances exceed a defined threshold.

How the community answered

(26 responses)
  • A
    4% (1)
  • B
    8% (2)
  • C
    12% (3)
  • D
    77% (20)

Community Discussion

No community discussion yet for this question.

Full JK0-017 Practice