Which of the following is the BEST way to manage stakeholder expectations?
The correct answer is C. Obtain stakeholder buy-in. See the full explanation below for the reasoning.
Question
Which of the following is the BEST way to manage stakeholder expectations?
Options
- AProvide the stakeholder with a copy of the project charter.
- BApprove stakeholder requests.
- CObtain stakeholder buy-in.
- DHave the stakeholders complete a change request form.
How the community answered
(28 responses)- A4% (1)
- B11% (3)
- C82% (23)
- D4% (1)