A project is nearing completion. Which of the following tasks is required to ensure continuity after the project closes?

The correct answer is A. Transition ownership to operational team. See the full explanation below for the reasoning.

Question

A project is nearing completion. Which of the following tasks is required to ensure continuity after the project closes?

Options

  • ATransition ownership to operational team
  • BExtended support delivered by project members
  • CEnsure the operation team provides warranty prior to handover
  • DPeriodic training of project team resources

How the community answered

(34 responses)
  • A
    76% (26)
  • B
    12% (4)
  • C
    3% (1)
  • D
    9% (3)