A project scope document would include which of the following? (Select TWO).

The correct answer is B. Key performance indicators C. Assumptions. See the full explanation below for the reasoning.

Question

A project scope document would include which of the following? (Select TWO).

Options

  • AWBS
  • BKey performance indicators
  • CAssumptions
  • DRisk matrix
  • ENetwork diagram

How the community answered

(60 responses)
  • A
    8% (5)
  • B
    85% (51)
  • D
    2% (1)
  • E
    5% (3)