JK0-017 · Question #272
Which of the following is required to validate a project?
The correct answer is D. Alignment with the organization's strategic goals. See the full explanation below for the reasoning.
Question
Which of the following is required to validate a project?
Options
- AProblem statement
- BSigned project charter
- CKey project deliverables
- DAlignment with the organization's strategic goals
How the community answered
(47 responses)- A9% (4)
- B2% (1)
- C4% (2)
- D85% (40)