CompTIA
JK0-017 · Question #266
A change request has been reviewed and denied by the project governance. Which of the following components should be updated by the project manager?
The correct answer is B. Change log. See the full explanation below for the reasoning.
Question
A change request has been reviewed and denied by the project governance. Which of the following components should be updated by the project manager?
Options
- AWBS
- BChange log
- CScope document
- DCommunications log
How the community answered
(27 responses)- A4% (1)
- B78% (21)
- C4% (1)
- D15% (4)
Community Discussion
No community discussion yet for this question.