While in an operations meeting, the project manager hears that a new enhancement is being released that will impact the agreed upon scope. Which of the following should the project manager do NEXT?
The correct answer is A. Identify the issue, perform an analysis, and create a change request. See the full explanation below for the reasoning.
Question
While in an operations meeting, the project manager hears that a new enhancement is being released that will impact the agreed upon scope. Which of the following should the project manager do NEXT?
Options
- AIdentify the issue, perform an analysis, and create a change request
- BLog the change and communicate it to the project team
- CInform the sponsor while allowing the change to continue
- DStop the development, communicating that changes have to be approved
How the community answered
(40 responses)- A73% (29)
- B15% (6)
- C8% (3)
- D5% (2)