As a way to systematically identify risks inherent to a project, which of the following tools would be used?

The correct answer is D. Risk Breakdown Structure. See the full explanation below for the reasoning.

Question

As a way to systematically identify risks inherent to a project, which of the following tools would be used?

Options

  • ARisk response plan
  • BRisk probability and impact matrix
  • CRisk Matrix
  • DRisk Breakdown Structure

How the community answered

(23 responses)
  • A
    4% (1)
  • B
    13% (3)
  • C
    4% (1)
  • D
    78% (18)