As a way to systematically identify risks inherent to a project, which of the following tools would be used?
The correct answer is D. Risk Breakdown Structure. See the full explanation below for the reasoning.
Question
As a way to systematically identify risks inherent to a project, which of the following tools would be used?
Options
- ARisk response plan
- BRisk probability and impact matrix
- CRisk Matrix
- DRisk Breakdown Structure
How the community answered
(23 responses)- A4% (1)
- B13% (3)
- C4% (1)
- D78% (18)