After completing a WBS, a project manager has been asked to identify human resource requirements. Which of the following should be included in the project plan?

The correct answer is A. Training needs. See the full explanation below for the reasoning.

Question

After completing a WBS, a project manager has been asked to identify human resource requirements. Which of the following should be included in the project plan?

Options

  • ATraining needs
  • BCommunication needs
  • CTransportation needs
  • DConflict resolution preferences

How the community answered

(27 responses)
  • A
    85% (23)