Which of the following components of a quality management plan is an initial quality measurement?
The correct answer is D. Quality baseline. See the full explanation below for the reasoning.
Question
Which of the following components of a quality management plan is an initial quality measurement?
Options
- AQuality specifications
- BQuality control
- CQuality assurance
- DQuality baseline
How the community answered
(31 responses)- A3% (1)
- B3% (1)
- C10% (3)
- D84% (26)