JK0-017 · Question #202

A project is struggling because the sponsor continually has to increase funding which may cause the project to get cancelled. This could have been avoided by using:

The correct answer is B. Change control. See the full explanation below for the reasoning.

Question

A project is struggling because the sponsor continually has to increase funding which may cause the project to get cancelled. This could have been avoided by using:

Options

  • AQuality metrics.
  • BChange control.
  • CAWBS.
  • DFixed costs.

How the community answered

(58 responses)
  • A
    16% (9)
  • B
    72% (42)
  • C
    3% (2)
  • D
    9% (5)