nerdexam
CompTIA

JK0-017 · Question #2

Which of the following would be included in a project scope document? (Select THREE).

The correct answer is A. Project constraints E. Key Performance Indicators (KPIs) F. Detailed project objectives. See the full explanation below for the reasoning.

Question

Which of the following would be included in a project scope document? (Select THREE).

Options

  • AProject constraints
  • BGantt chart
  • CWork Breakdown Structure (WBS)
  • DProject roles and responsibilities
  • EKey Performance Indicators (KPIs)
  • FDetailed project objectives

How the community answered

(45 responses)
  • A
    80% (36)
  • B
    11% (5)
  • C
    7% (3)
  • D
    2% (1)

Community Discussion

No community discussion yet for this question.

Full JK0-017 Practice