A change request has been approved for a project. Which of the following actions should be taken FIRST by the project manager?

The correct answer is C. Update the appropriate project plan documents. See the full explanation below for the reasoning.

Question

A change request has been approved for a project. Which of the following actions should be taken FIRST by the project manager?

Options

  • APerform an analysis to determine the impact on the project
  • BCreate an updated Pareto chart
  • CUpdate the appropriate project plan documents
  • DIdentify project cost and schedule variances

How the community answered

(29 responses)
  • A
    14% (4)
  • B
    3% (1)
  • C
    76% (22)
  • D
    7% (2)