An unexpected risk has been identified in a project. Which of the following actions should the project manager perform FIRST?
The correct answer is A. Add the risk to the risk register. See the full explanation below for the reasoning.
Question
An unexpected risk has been identified in a project. Which of the following actions should the project manager perform FIRST?
Options
- AAdd the risk to the risk register
- BUpdate the project probability / impact matrix
- CSubmit a change request
- DPerform a risk qualitative analysis
How the community answered
(30 responses)- A73% (22)
- B7% (2)
- C17% (5)
- D3% (1)