A project manager has calculated their project to have a SV of -$5,000. Which of the following conclusions is correct?

The correct answer is C. The project is behind schedule. See the full explanation below for the reasoning.

Question

A project manager has calculated their project to have a SV of -$5,000. Which of the following conclusions is correct?

Options

  • AThe project is over budget
  • BThe project baseline is incorrect
  • CThe project is behind schedule
  • DThe project is under budget

How the community answered

(28 responses)
  • A
    11% (3)
  • B
    4% (1)
  • C
    82% (23)
  • D
    4% (1)