A project manager has calculated their project to have a SV of -$5,000. Which of the following conclusions is correct?
The correct answer is C. The project is behind schedule. See the full explanation below for the reasoning.
Question
A project manager has calculated their project to have a SV of -$5,000. Which of the following conclusions is correct?
Options
- AThe project is over budget
- BThe project baseline is incorrect
- CThe project is behind schedule
- DThe project is under budget
How the community answered
(28 responses)- A11% (3)
- B4% (1)
- C82% (23)
- D4% (1)