JK0-017 · Question #171
Which of the following describes a critical path?
The correct answer is D. The order of activities that takes the longest to complete. See the full explanation below for the reasoning.
Question
Which of the following describes a critical path?
Options
- ADeliverables that need to be developed for project completion
- BTimeline that the resources roll on to the project
- CThe earliest schedule that a project can finish all of its activities
- DThe order of activities that takes the longest to complete
How the community answered
(28 responses)- A11% (3)
- B4% (1)
- C4% (1)
- D82% (23)