A project is in the execution phase. In review, Joe sees that the project will miss the next deadline due to delays in equipment delivery. Joe has asked the resource manager for additional…
The correct answer is A. Crash the schedule. See the full explanation below for the reasoning.
Question
A project is in the execution phase. In review, Joe sees that the project will miss the next deadline due to delays in equipment delivery. Joe has asked the resource manager for additional resources, has been denied, and reminded that the deadline cannot be missed. Which of the following is the BEST option to meet the deadline?
Options
- ACrash the schedule
- BLog the risk in the risk register
- CHe should perform the work needed
- DReport to the project sponsor that the deadline will be missed
How the community answered
(69 responses)- A83% (57)
- B4% (3)
- C10% (7)
- D3% (2)
Community Discussion