JK0-017 · Question #163
After which of the following documents is signed off by stakeholders can a project begin?
The correct answer is B. Project charter. See the full explanation below for the reasoning.
Question
After which of the following documents is signed off by stakeholders can a project begin?
Options
- AProject stakeholder requirements
- BProject charter
- CProject scope
- DProject schedule
How the community answered
(40 responses)- A5% (2)
- B78% (31)
- C5% (2)
- D13% (5)