nerdexam
CompTIA

JK0-017 · Question #155

A project team is reviewing the deliverables and identifies a deliverable no one on the team has experience with. The lack of expertise is identified as a risk. The project manager decides, as a…

The correct answer is A. Transference. See the full explanation below for the reasoning.

Question

A project team is reviewing the deliverables and identifies a deliverable no one on the team has experience with. The lack of expertise is identified as a risk. The project manager decides, as a workaround, to contract with a third party. This type of risk response is called:

Options

  • ATransference.
  • BAvoidance.
  • CMonitor and Prepare.
  • DAcceptance.

How the community answered

(34 responses)
  • A
    71% (24)
  • B
    18% (6)
  • C
    3% (1)
  • D
    9% (3)

Community Discussion

No community discussion yet for this question.

Full JK0-017 Practice