CompTIA
JK0-017 · Question #155
A project team is reviewing the deliverables and identifies a deliverable no one on the team has experience with. The lack of expertise is identified as a risk. The project manager decides, as a…
The correct answer is A. Transference. See the full explanation below for the reasoning.
Question
A project team is reviewing the deliverables and identifies a deliverable no one on the team has experience with. The lack of expertise is identified as a risk. The project manager decides, as a workaround, to contract with a third party. This type of risk response is called:
Options
- ATransference.
- BAvoidance.
- CMonitor and Prepare.
- DAcceptance.
How the community answered
(34 responses)- A71% (24)
- B18% (6)
- C3% (1)
- D9% (3)
Community Discussion
No community discussion yet for this question.