CompTIA
JK0-017 · Question #153
Which of the following risk response planning techniques is a project manager using when they are changing the project plan to remove the risks impact?
The correct answer is D. Avoidance. See the full explanation below for the reasoning.
Question
Which of the following risk response planning techniques is a project manager using when they are changing the project plan to remove the risks impact?
Options
- ATransference
- BMitigation
- CAcceptance
- DAvoidance
How the community answered
(32 responses)- A13% (4)
- B6% (2)
- C3% (1)
- D78% (25)
Community Discussion
No community discussion yet for this question.