The project sponsor has asked for the project to be delivered two months earlier than originally planned with no changes to the deliverables, cost, or the project team. Which of the following…
The correct answer is A. Optimizing. See the full explanation below for the reasoning.
Question
The project sponsor has asked for the project to be delivered two months earlier than originally planned with no changes to the deliverables, cost, or the project team. Which of the following schedule planning techniques could be used to meet this request?
Options
- AOptimizing
- BCrashing
- CDelaying
- DResource leveling
How the community answered
(45 responses)- A78% (35)
- B7% (3)
- C2% (1)
- D13% (6)