nerdexam
CompTIA

JK0-017 · Question #148

The project sponsor has asked for the project to be delivered two months earlier than originally planned with no changes to the deliverables, cost, or the project team. Which of the following…

The correct answer is A. Optimizing. See the full explanation below for the reasoning.

Question

The project sponsor has asked for the project to be delivered two months earlier than originally planned with no changes to the deliverables, cost, or the project team. Which of the following schedule planning techniques could be used to meet this request?

Options

  • AOptimizing
  • BCrashing
  • CDelaying
  • DResource leveling

How the community answered

(45 responses)
  • A
    78% (35)
  • B
    7% (3)
  • C
    2% (1)
  • D
    13% (6)

Community Discussion

No community discussion yet for this question.

Full JK0-017 Practice