Which of the following should the project charter include?
The correct answer is B. A project description. See the full explanation below for the reasoning.
Question
Which of the following should the project charter include?
Options
- AA risk register
- BA project description
- CA post-mortem analysis
- DAn issues log
How the community answered
(44 responses)- A11% (5)
- B80% (35)
- C2% (1)
- D7% (3)