A project manager is involved with minimizing unauthorized changes to the project. Which of the following will BEST assist with these changes?
The correct answer is C. Scope statement. See the full explanation below for the reasoning.
Question
A project manager is involved with minimizing unauthorized changes to the project. Which of the following will BEST assist with these changes?
Options
- ARisk register
- BQuality management metrics
- CScope statement
- DBudget scope
How the community answered
(23 responses)- A17% (4)
- B4% (1)
- C70% (16)
- D9% (2)