Which of the following techniques modifies the schedule based upon resource constraints?

The correct answer is A. Critical Chain Method. See the full explanation below for the reasoning.

Question

Which of the following techniques modifies the schedule based upon resource constraints?

Options

  • ACritical Chain Method
  • BCritical Path Method
  • CArrow Diagramming Method
  • DPrecedence Diagramming Method

How the community answered

(20 responses)
  • A
    80% (16)
  • B
    10% (2)
  • C
    5% (1)
  • D
    5% (1)