JK0-017 · Question #108
Task B is not planned to start until Task A is completed. Task A is delayed and will not be completed on time. Starting Task B prior to Task A completing is an example of:
The correct answer is B. Fast tracking. See the full explanation below for the reasoning.
Question
Task B is not planned to start until Task A is completed. Task A is delayed and will not be completed on time. Starting Task B prior to Task A completing is an example of:
Options
- AManaging change
- BFast tracking
- CRolling wave planning
- DCrashing
How the community answered
(37 responses)- A8% (3)
- B73% (27)
- C16% (6)
- D3% (1)