Task B is not planned to start until Task A is completed. Task A is delayed and will not be completed on time. Starting Task B prior to Task A completing is an example of:

The correct answer is B. Fast tracking. See the full explanation below for the reasoning.

Question

Task B is not planned to start until Task A is completed. Task A is delayed and will not be completed on time. Starting Task B prior to Task A completing is an example of:

Options

  • AManaging change
  • BFast tracking
  • CRolling wave planning
  • DCrashing

How the community answered

(37 responses)
  • A
    8% (3)
  • B
    73% (27)
  • C
    16% (6)
  • D
    3% (1)