BCS-ISEB
ITILF2011 · Question #411
ITILF2011 Question #411: Real Exam Question with Answer & Explanation
The correct answer is A. The contract is being negotiated. See the full explanation below for the reasoning.
Question
A plan for managing the end of a supplier contract should be created when?
Options
- AThe contract is being negotiated
- BThe contract is about to be ended
- CThe Supplier Manager decides that there is a risk the contract might need to end soon
- DThe contract has been agreed
Community Discussion
No community discussion yet for this question.