PeopleCert
ITIL · Question #401
ITIL Question #401: Real Exam Question with Answer & Explanation
The correct answer is D: 2 only. In ITIL Availability Management, proactive activities are performed in advance to prevent failures, while reactive activities respond to failures after detection. Only designing availability into a solution qualifies as proactive.
Question
Which of the following availability management activities are considered to be proactive as opposed to reactive? (1) Monitoring system availability (2) Designing availability into a proposed solution
Options
- ANeither of the above
- BBoth of the above
- C1 only
- D2 only
Explanation
In ITIL Availability Management, proactive activities are performed in advance to prevent failures, while reactive activities respond to failures after detection. Only designing availability into a solution qualifies as proactive.
Common mistakes.
- A. This is incorrect because item 2 - designing availability into a solution - is clearly a proactive availability management activity.
- B. Both items cannot be proactive because monitoring (item 1) is a reactive or detective control that identifies problems after they emerge, not before.
- C. Monitoring alone is not proactive; it responds to availability events as they occur rather than preventing them through advance design decisions.
Concept tested. Proactive vs reactive Availability Management activities
Reference. https://www.axelos.com/resource-hub/glossary
Community Discussion
No community discussion yet for this question.