nerdexam
ExamsITILQuestions#401
PeopleCert

ITIL · Question #401

ITIL Question #401: Real Exam Question with Answer & Explanation

The correct answer is D: 2 only. In ITIL Availability Management, proactive activities are performed in advance to prevent failures, while reactive activities respond to failures after detection. Only designing availability into a solution qualifies as proactive.

Question

Which of the following availability management activities are considered to be proactive as opposed to reactive? (1) Monitoring system availability (2) Designing availability into a proposed solution

Options

  • ANeither of the above
  • BBoth of the above
  • C1 only
  • D2 only

Explanation

In ITIL Availability Management, proactive activities are performed in advance to prevent failures, while reactive activities respond to failures after detection. Only designing availability into a solution qualifies as proactive.

Common mistakes.

  • A. This is incorrect because item 2 - designing availability into a solution - is clearly a proactive availability management activity.
  • B. Both items cannot be proactive because monitoring (item 1) is a reactive or detective control that identifies problems after they emerge, not before.
  • C. Monitoring alone is not proactive; it responds to availability events as they occur rather than preventing them through advance design decisions.

Concept tested. Proactive vs reactive Availability Management activities

Reference. https://www.axelos.com/resource-hub/glossary

Community Discussion

No community discussion yet for this question.

Full ITIL Practice