ITIL · Question #386

Which of the following activities is NOT a part of the Deming Cycle?

The correct answer is D. Coordinate. The Deming Cycle (also called PDCA) has exactly four phases - Plan, Do, Check, and Act. 'Coordinate' is not one of them.

Key principles and models

Question

Which of the following activities is NOT a part of the Deming Cycle?

Options

  • AAct
  • BPlan
  • CDo
  • DCoordinate

How the community answered

(60 responses)
  • A
    5% (3)
  • B
    2% (1)
  • D
    93% (56)

Why each option

The Deming Cycle (also called PDCA) has exactly four phases - Plan, Do, Check, and Act. 'Coordinate' is not one of them.

AAct

Act is the fourth phase of the Deming Cycle, where adjustments are made based on Check phase findings.

BPlan

Plan is the first phase of the Deming Cycle, where objectives and processes are established.

CDo

Do is the second phase of the Deming Cycle, where the plan is implemented on a small scale.

DCoordinateCorrect

'Coordinate' does not exist as a phase in the Deming Cycle. The four phases are Plan, Do, Check, and Act, forming a continuous loop for quality improvement and process management.

Concept tested: Deming Cycle PDCA phases identification

Source: https://asq.org/quality-resources/pdca-cycle

Topics

#Deming Cycle#PDCA#CSI#quality management

Community Discussion

No community discussion yet for this question.