ITIL · Question #129

ITIL Question #129: Real Exam Question with Answer & Explanation

The correct answer is D: Co-ordinate. The Deming Cycle (PDCA) has exactly four phases: Plan, Do, Check, and Act. 'Co-ordinate' is not one of these phases and does not belong to the model.

Question

Which one of the following activities is NOT part of the Deming Cycle?

Options

  • AAct
  • BPlan
  • CDo
  • DCo-ordinate

Explanation

The Deming Cycle (PDCA) has exactly four phases: Plan, Do, Check, and Act. 'Co-ordinate' is not one of these phases and does not belong to the model.

Common mistakes.

  • A. Act is the fourth phase of the Deming Cycle, where results are reviewed and successful changes are standardized or the cycle is restarted.
  • B. Plan is the first phase of the Deming Cycle, where goals, processes, and hypotheses for improvement are established.
  • C. Do is the second phase of the Deming Cycle, where the planned change is implemented, typically on a small or pilot scale.

Concept tested. Deming Cycle PDCA phases in service management

Reference. https://asq.org/quality-resources/pdca-cycle