ISO20KF · Question #68

Which processes should the Plan, Do, Check, Act methodology be applied to?

The correct answer is A. all of the processes in scope of ISO/IEC 20000. See the full explanation below for the reasoning.

Question

Which processes should the Plan, Do, Check, Act methodology be applied to?

Options

  • Aall of the processes in scope of ISO/IEC 20000
  • Bthe Planning & Implementing Service Management process
  • Cthe Requirements for a Management System process
  • Dthose that support business critical services

How the community answered

(48 responses)
  • A
    77% (37)
  • B
    15% (7)
  • C
    6% (3)
  • D
    2% (1)