A group of activities within Release Management is roll-out, distribution and installation. What should be ensured as part of these activities?

The correct answer is C. Correct. This is a best practice according to the standard. See the full explanation below for the reasoning.

Question

A group of activities within Release Management is roll-out, distribution and installation. What should be ensured as part of these activities?

Options

  • AIncorrect. This is part of Change Management as opposed to Release Management.
  • BIncorrect. This is part of the documentation procedure, not of the roll-out, distribution and
  • CCorrect. This is a best practice according to the standard.
  • DIncorrect. This is part of Release verification and acceptance.

How the community answered

(56 responses)
  • A
    7% (4)
  • B
    13% (7)
  • C
    77% (43)
  • D
    4% (2)

Community Discussion

No community discussion yet for this question.