You are the project manager of a project .You have just completed the Collect Requirements and Define Scope. What should you do next?

The correct answer is B. Create WBS. You've hit your session limit · resets 10:20pm (America/New_York)

Project Planning

Question

You are the project manager of a project .You have just completed the Collect Requirements and Define Scope. What should you do next?

Options

  • AControl Scope
  • BCreate WBS
  • CValue analysis
  • DVerify Scope

How the community answered

(57 responses)
  • A
    2% (1)
  • B
    81% (46)
  • C
    12% (7)
  • D
    5% (3)

Explanation

You've hit your session limit · resets 10:20pm (America/New_York)

Topics

#scope management#WBS#planning process sequence#scope definition