ISEB-PM1 · Question #91

You are a project manager for Pizza Direct, which is a retail pizza delivery store. Your company is competing with another retail store for the option of opening two new stores in a foreign country…

The correct answer is C. You decline to participate in the initial meetings with the foreign business partners because of. ISEB ISEB-PM1 Exam

Business Concepts

Question

You are a project manager for Pizza Direct, which is a retail pizza delivery store. Your company is competing with another retail store for the option of opening two new stores in a foreign country. You know, but have not yet informed your company, that you are going to go to work for the competitor, which happens to be bidding for this same opportunity. What is the most appropriate response?

Options

  • AYou decide to participate in the initial meetings with the foreign business partners because any
  • BYou inform the foreign business partners that you're going to be working with a new company
  • CYou decline to participate in the initial meetings with the foreign business partners because of
  • DYou've not yet received an official offer from the competing company for your new job

How the community answered

(28 responses)
  • A
    14% (4)
  • B
    4% (1)
  • C
    79% (22)
  • D
    4% (1)

Explanation

ISEB ISEB-PM1 Exam

Topics

#professional ethics#conflict of interest#PMI code of conduct#disclosure