ISEB-PM1 · Question #90

The inputs of the Performance Reporting process include all of the following except for which one?

The correct answer is A. Performance reviews. You've hit your session limit · resets 10:20pm (America/New_York)

Project Control

Question

The inputs of the Performance Reporting process include all of the following except for which one?

Options

  • APerformance reviews
  • BWork performance information
  • CForecasted completion
  • DPerformance measurements

How the community answered

(48 responses)
  • A
    79% (38)
  • B
    2% (1)
  • C
    13% (6)
  • D
    6% (3)

Explanation

You've hit your session limit · resets 10:20pm (America/New_York)

Topics

#performance reporting#process inputs#monitoring and controlling#earned value management