ISEB-PM1 · Question #90
The inputs of the Performance Reporting process include all of the following except for which one?
The correct answer is A. Performance reviews. You've hit your session limit · resets 10:20pm (America/New_York)
Project Control
Question
The inputs of the Performance Reporting process include all of the following except for which one?
Options
- APerformance reviews
- BWork performance information
- CForecasted completion
- DPerformance measurements
How the community answered
(48 responses)- A79% (38)
- B2% (1)
- C13% (6)
- D6% (3)
Explanation
You've hit your session limit · resets 10:20pm (America/New_York)
Topics
#performance reporting#process inputs#monitoring and controlling#earned value management
Community Discussion
No community discussion yet for this question.