To-complete performance index (TCPI) is represented by which of the following?
The correct answer is A. BAC - EV/BAC - AC. You've hit your session limit · resets 10:20pm (America/New_York)
Project Control
Question
To-complete performance index (TCPI) is represented by which of the following?
Options
- ABAC - EV/BAC - AC
- BA measure of the value of work completed compared to the actual cost or progress
- CA measure of progress achieved compared to progress planned
- DAC + (BAC - EV)
How the community answered
(28 responses)- A86% (24)
- B4% (1)
- C4% (1)
- D7% (2)
Explanation
You've hit your session limit · resets 10:20pm (America/New_York)
Topics
#TCPI#earned value management#EVM formulas#cost performance