nerdexam
BCS-ISEB

ISEB-PM1 · Question #89

To-complete performance index (TCPI) is represented by which of the following?

The correct answer is A. BAC - EV/BAC - AC. You've hit your session limit · resets 10:20pm (America/New_York)

Project Control

Question

To-complete performance index (TCPI) is represented by which of the following?

Options

  • ABAC - EV/BAC - AC
  • BA measure of the value of work completed compared to the actual cost or progress
  • CA measure of progress achieved compared to progress planned
  • DAC + (BAC - EV)

How the community answered

(28 responses)
  • A
    86% (24)
  • B
    4% (1)
  • C
    4% (1)
  • D
    7% (2)

Explanation

You've hit your session limit · resets 10:20pm (America/New_York)

Topics

#TCPI#earned value management#EVM formulas#cost performance

Community Discussion

No community discussion yet for this question.

Full ISEB-PM1 Practice