BCS-ISEB
ISEB-PM1 · Question #81
Which of the following would be the MOST appropriate thing to do during the planning process group?
The correct answer is D. Work with the customer to determine acceptance criteria. You've hit your session limit · resets 10:20pm (America/New_York)
Project Planning
Question
Which of the following would be the MOST appropriate thing to do during the planning process group?
Options
- AUpdate corporate processes and procedures based on lessons learned.
- BEvaluate the effectiveness of risk responses.
- CRecommend changes and defect repair.
- DWork with the customer to determine acceptance criteria.
How the community answered
(25 responses)- A8% (2)
- B4% (1)
- C4% (1)
- D84% (21)
Explanation
You've hit your session limit · resets 10:20pm (America/New_York)
Topics
#planning process group#acceptance criteria#customer requirements#project planning
Community Discussion
No community discussion yet for this question.