ISEB-PM1 · Question #627

What is the best reason to create a work breakdown structure?

The correct answer is C. It helps attain buy-in from the team doing the work. You've hit your weekly limit · resets 5am (America/New_York)

Project Planning

Question

What is the best reason to create a work breakdown structure?

Options

  • AIt provides authority for the Project Manager
  • BIt allows the project budget to be determined
  • CIt helps attain buy-in from the team doing the work
  • DIt allows the project completion date to be determined